Sound Transit Board Approves Opening for 8 Stations

The Sound Transit Board approved opening the eight-station segment for service prior to completion of the full East Link Extension.  

Sound Transit Board Approves Opening for 8 Stations

Service on the 2 Line is proposed to run with two-car trains every 10 minutes, 16 hours a day.

Photo: Sound Transit

2 min to read


Sound Transit announced that the Link 2 Line can begin operating passenger service between South Bellevue and Redmond Technology stations in Spring 2024.

The Sound Transit Board approved opening the eight-station segment for service prior to completion of the full East Link Extension.  

Ad Loading...

Service on the 2 Line is proposed to run with two-car trains every 10 minutes, 16 hours a day. The final service level will be approved by the Sound Transit Board as part of the 2024 Service Plan. This action is expected in October.

What the 2 Line Service Will Offer

This initial 2 Line service will offer Eastside passengers traffic-free trips between South Bellevue and Redmond Technology stations.

Service will also connect passengers to Overlake Medical Center, the Spring District, and the BelRed area. 

The Board’s action included provisions to meet ridership demand on the 1 Line, including maximizing peak-hour service, adding bus service in Snohomish County, and support for Lynnwood passengers until the opening of the full East Link Extension.

“It’s an exciting step to connect more communities via fast, carbon-free Link light rail, and opening these stations on the Eastside is the opening act of the 2 Line,” said Dow Constantine, Sound Transit Board chair. “From Redmond to Bellevue, people have a new option to get to work, school, and all the things that make this community special, and I’m excited to see what’s next when the 2 Line crosses Lake Washington in 2025.”

Ad Loading...

Sound Transit Working on 2 Line Plans

Sound Transit is working with regional transit partners on plans to coordinate the 2 Line opening with other spring service changes on ST Express, King County Metro Transit, and Community Transit bus routes.

Existing ST Express and King County Metro routes including Route 550, B Line, and other local routes are anticipated to continue operating on their current routes until the full 2 Line opens in 2025.

Voters approved the East Link Extension in 2008 as part of the Sound Transit 2 ballot measure.

Construction on the project began in 2017, including sequential excavation mining of the one-half-mile Bellevue tunnel, which was completed in 2020.

Light rail test trains have been operating across the alignment to test the overhead electrical power system and train signal system, and simulated service is expected to begin in early 2024.

Ad Loading...

The Sound Transit Board authorized up to $43 million from the existing East Link Extension $3.68 billion budget to fund the activities necessary to open the East Link Starter Line in Spring 2024.

More Rail

A New York MTA subway car with an open gangway
Railby StaffMarch 20, 2026

New York MTA Seeks Bids for 2,390 Subway Cars in Record-Breaking Order

The new cars, model R262, will be funded by the MTA’s 2025-29 Capital Plan, which received a historic $68 billion in funding from Governor Hochul and the State Legislature in the FY26 Enacted State Budget.

Read More →
Graphic from Amtrak promoting the B&P Tunnel Replacement and Frederick Douglass Tunnel project, featuring the Amtrak logo, project title and an illustration of a high-speed train near the West Baltimore MARC Station.
Railby News/Media ReleaseMarch 17, 2026

Amtrak Announces Community Grants for Projects Near Baltimore’s New Frederick Douglass Tunnel

Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.

Read More →
Amtrak train with logo
Railby StaffMarch 16, 2026

Amtrak Marks Restoration of Two South Carolina Stations

The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.

Read More →
Ad Loading...
A view looking down the rail across the new Portal North Bridge.
Railby Staff and News ReportsMarch 13, 2026

NJ Transit, Amtrak Prepare to Open First Track on New Portal North Bridge

The new bridge will begin carrying passenger trains on March 16, replacing a 116-year-old swing bridge that has long caused delays.

Read More →
Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Ad Loading...
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
Ad Loading...
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →