Sound Transit Sets Schedule for Stride BRT

Sound Transit expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Sound Transit Sets Schedule for Stride BRT

There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3.

Photo: Sound Transit

3 min to read


The Sound Transit Board adopted a final budget and schedule for the new Stride bus rapid transit (BRT) service, including a new bus base and BRT lines on SR 522/NE 145th Street and I- 405.

Sound Transit said it expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Ad Loading...

BRT was part of Sound Transit’s 2016 voter-approved system expansion program ST3. Stride will provide high-capacity transit service with connections to light rail in Bellevue, Tukwila, Shoreline, and Lynnwood. 

When Stride begins operating, trips between Bellevue and Burien will take approximately 40 minutes; trips between Lynnwood and Bellevue will take approximately 35 minutes; and trips between Shoreline and Bothell will take approximately 37 minutes.

These travel times are an average of 20 minutes faster than the current ST Express bus service in these areas. 

“Today’s action is a significant step forward in expanding and connecting our regional high-capacity transit network,” said Sound Transit Board chair Dow Constantine. “Stride will provide fast, frequent reliable service to thousands of riders on the I-405 and SR 522 corridors, and seamless connections to Link light rail and regional bus services. We look forward to beginning construction on these BRT projects.”

The Stride project includes the Bus Base North, and BRT lines between Lynnwood and Burien on I-405, I-5, and SR 518 (S1 and S2), and between Shoreline and Bothell on SR 522/NE 145th (S3). The combined budget for the Stride BRT program is $2.35 billion.

Ad Loading...

This total budget exceeds the re-alignment cost estimate as assumed in the financial plan by approximately 14%. Factors contributing to additional costs include inflation, market factors, scope changes, and schedule impacts. 

Bus Base North (BBN)

The Bus Base North will be the first Sound Transit bus operations and maintenance base, serving the full Stride BRT fleet and a portion of the ST Express fleet, with a total capacity of 120 buses.

The operating facility will provide storage, maintenance, charging, fueling, washing, repairs, and deployment of the bus fleet. 

The Stride bus fleet will include Sound Transit's first battery-electric buses, for a cleaner, more sustainable way to travel in the region. There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3. Coaches will be in operation most of the day, charging each time they lay over at route termini.

The BBN is expected to open for service in the fourth quarter of 2027. The approved budget for the Bus Base North is $499.5 million.

Ad Loading...

I-405 Stride Bus Rapid Transit

The I-405 BRT project will establish a BRT system from the Lynnwood Transit Center to the Burien Transit Center via I-5, I-405, and SR 518.

The project consists of several elements, including new and upgraded transit centers, limited new park-and-ride capacity, freeway BRT stations, and non-motorized access improvements to the stations.

Sound Transit components that are within WSDOT’s Brickyard to SR 527 Improvement Project are part of the I-405 BRT north line (S2).

The I-405 BRT will connect to the regional transit system at three Link light rail stations and the SR 522/NE 145th BRT line.

The Stride S1 line between Burien and Bellevue is expected to open in the third quarter of 2028, and the Stride S2 line between Lynnwood and Bellevue is expected to open in the second quarter of 2029.

Ad Loading...

The approved budget for the I-405 BRT project is $1.27 billion. 

SR 522/NE 145th Street Stride Bus Rapid Transit

The SR 522/NE 145th BRT Project establishes BRT service along the corridor, primarily operating in business access and transit (BAT) and bus queue bypass lanes for nine miles between Shoreline and Bothell, with separate, connecting service options to Woodinville. The Stride S3 line is expected to open in the second quarter of 2028.

The approved budget for the SR 522/NE 145th Street BRT project is $581.5 million.

More Bus

Cover photo for Part 2 with Cecil Blandon
Managementby Alex RomanApril 30, 2026

Bus Tech Talk: Part 2 with AC Transit’s Cecil Blandon

Deck: In Part 2 of a two-part conversation, AC Transit’s director of maintenance joins co-hosts Alex Roman and Mark Hollenbeck to discuss his maintenance team’s work with various types of vehicle, training, augmented reality, and more.

Read More →
A Valley Metro bus
Managementby StaffApril 28, 2026

Keolis Contract Extended for Valley Metro's East Valley Fixed-Route Bus Service

Under this extension, Keolis will continue to manage and operate fixed-route bus service across the East Valley, serving communities including Tempe, Mesa, Chandler, Scottsdale, the town of Gilbert, parts of Phoenix, and the Gila River Indian Community.

Read More →
A Des Moines DART bus
Busby StaffApril 28, 2026

Iowa DART Prepares for June Bus Network Launch

The new network reflects extensive input from riders and the community through Reimagine DART on what matters most in public transit — and those priorities are reflected in the changes ahead.

Read More →
Ad Loading...
A Route 8 bus travels on Denny Way in congested traffic.
Busby StaffApril 24, 2026

Seattle Speeds up Service on Denny Way

A new bus lane project aims to improve reliability on one of King County Metro’s busiest and most congestion-prone corridors.

Read More →
WMATA 7000-series railcars at Navy Yard
Managementby StaffApril 24, 2026

WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares

While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.

Read More →
A WMATA bus underneath a cherry blossom tree
Busby Alex RomanApril 24, 2026

Bus Coalition Leaders Push to Protect Transit Funding in Critical Reauthorization Year

Coalition leaders outline priorities for preserving bus funding, maintaining competitive grants, and ensuring flexibility for transit agencies nationwide.

Read More →
Ad Loading...
A Community Transit Swift Articulated Bus
Managementby StaffApril 23, 2026

City of Everett, Community Transit Advance Transit Consolidation Effort

In the coming months, the parties will develop an interlocal agreement for the city’s annexation into Community Transit’s district. The proposal will be considered by the Everett City Council and the Community Transit board this fall, said officials.

Read More →
Cincinnati Metro's new battery-electric bus, which was unveiled on Earth Day
Zero Emissionsby StaffApril 23, 2026

Cincinnati Metro Goes Electric

Two battery-electric buses entered service on Earth Day, with four additional vehicles expected to join the fleet this summer. Seven more buses are planned for the end of 2027, bringing Metro’s total zero-emission fleet to 13.

Read More →
A photo of a San Antonio VIA Metropolitan Transit zero-emission bus.
Busby Staff and News ReportsApril 20, 2026

Recovery and Risk Define the Transit Bus Market in 2025

A 5% rise in deliveries and a surge in zero-emission buses signaled progress in 2025, but high costs, long lead times, and shifting funding priorities continue to cloud the outlook.

Read More →
Ad Loading...
A picture of a San Diego MTS railcar and bus at a transit station.
Managementby StaffApril 17, 2026

San Diego Transit Agencies Propose Fare Hike to Close Budget Gaps

The agencies, San Diego MTS and NCTD - San Diego Railroad, which share a fare system (PRONTO), proposed the changes to help address their respective financial sustainability strategies.

Read More →