With the Red Line work completed, the weekend will be free of any scheduled track work going into New Year's Eve when train service systemwide will be extended to 2 a.m. to accommodate workers and revelers ringing in the new year.
Service on the Red Line has been suspended since Dec. 18, to repair the deteriorating concrete beams and ceiling that date to the system’s original construction.
Photo: WMATA
2 min to read
The Washington Metropolitan Area Transit Authority (WMATA) announced Red Line construction between the Dupont Circle and Gallery Place stations will be completed early and $250,000 under budget, following construction for critical tunnel repairs and infrastructure upgrades, with normal Red Line services re-launching Dec. 30.
With the Red Line work completed, the weekend will be free of any scheduled track work going into New Year's Eve when train service systemwide will be extended to 2 a.m. to accommodate workers and revelers ringing in the new year.
Ad Loading...
In addition, 24/7 DC bus service is now available on 14 routes for those in the District traveling after the rail system closes.
Red Line Service
Service on the Red Line has been suspended since Dec. 18, to repair the deteriorating concrete beams and ceiling that date to the system’s original construction. Additionally, the work zone was extended Dec. 22 to 24 with no Red Line service between Gallery Place and Union Station.
Free shuttle buses replaced trains during construction, providing more than 172,000 passenger trips to date between the affected stations.
"We appreciate all of our customers, businesses, the District and the effort our Metro staff who worked through the holidays to get this critical work done," said WMATA GM/CEO Randy Clarke. “Maintaining the safety and reliability of the system is vital. Thanks to Mayor Bowser and the District Department of Transportation, we were able to use special dedicated bus lanes created for this project to minimize the impact to customers.”
Construction Highlights
Red Line construction highlights included:
Ad Loading...
WMATA’s construction team used more than eight tons of concrete and 466 pounds of rebar to rebuild the Red Line tunnel ceiling to prevent concrete from falling onto trains.
The team replaced 3,159 linear feet of running rail between Farragut North and Metro Center.
Workers installed 1,152 lights for the new platform edge lighting between Farragut North and Judiciary Sq with brighter, more sustainable LED lights.
Added extra insulation to the third rail power cables between Gallery Place and Judiciary Square to provide a moisture barrier of the electrified third rail, which powers the trains.
To prepare for its next generation train signaling system, Metro installed 15,914 linear feet of fiber optic cables between Farragut North and Judiciary Sq.
The Red Line construction is part of WMATA's 10-year, $15 billion Capital Improvement Program, investing in system safety, reliability, and the region's economy. The capital program will improve the customer experience and keep the region's infrastructure in a state of good repair.
Nadine S. Lee, who has served as president/CEO since July 2021, said the decision comes after careful reflection on the agency’s progress and its path forward.
In this edition of Biz Briefs, we highlight the latest developments shaping the future of mobility — from manufacturers and technology providers to transit agencies and motorcoach service operators.
As part of the contract, the AECOM-LiRo NYPennT Joint Venture will work with Amtrak and the selected Master Developer to completely transform Penn Station, improving safety and operational efficiency, making the system more family-friendly, accommodating increased train and passenger capacity, and delivering a world-class experience to its growing passenger base, according to Amtrak officials.
Company officials said that this latest contract extension with Metrolinx consolidates the company’s position as the leading private provider of Operations and maintenance services in North America.
The new cars, model R262, will be funded by the MTA’s 2025-29 Capital Plan, which received a historic $68 billion in funding from Governor Hochul and the State Legislature in the FY26 Enacted State Budget.
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.