Amtrak Awards 'Delivery Partner' Contract for Baltimore Tunnel Project

In a Delivery Partner model, the private partner shares Amtrak’s risk to deliver the program and is incentivized to help Amtrak achieve overall Program outcomes.

April 4, 2024
Amtrak Awards 'Delivery Partner' Contract for Baltimore Tunnel Project

Early work on the Frederick Douglass Tunnel Programbegan in 2023, with demolition currently underway and major construction slated to begin later this year, including utility relocations and work for the first of five bridges.

Photo: Amtrak

2 min to read


Amtrak awarded its first-ever “Delivery Partner” contract — an innovative construction management approach that will help drive successful execution of the $6 billion Frederick Douglass Tunnel Program, the company’s single largest capital project.

The award follows a competitive procurement process that began in early 2023

Ad Loading...

“We’re proud to award this important Delivery Partner contract that will help continue the positive momentum for the Frederick Douglass Tunnel Program,” said Amtrak Executive VP, Capital Delivery, Laura Mason. “Amtrak has built an industry-leading Capital Delivery department and continues to leverage innovative project delivery approaches like this, as we work to replace and modernize our critical infrastructure assets.”

Amtrak’s “Delivery Partner” Model

In a Delivery Partner model, the private partner shares Amtrak’s risk to deliver the program and is incentivized to help Amtrak achieve overall Program outcomes.

The Delivery Partner’s work will include design oversight, construction management, contract management and other administrative support, among other tasks.

The selected team, ADVANCE — a joint venture between major infrastructure firms AECOM and Jacobs — will establish an integrated program management team alongside Amtrak’s in-house Capital Delivery department to advance the program through completion.

The ADVANCE team has a demonstrated track record managing delivery partner and CMAR contracts for rail tunneling and train station projects around the world.

Ad Loading...

The team features a consortium of industry-leading firms, including Sener, Turner, & Townsend; RailPros; Aldea; and Dr. Sauer, as well as 22 additional highly qualified disadvantaged and small business enterprises (DBE/SBE) that will help meet the Delivery Partner’s 14% DBE/SBE goal.

“We’re excited to welcome the ADVANCE team onboard and appreciate the experience they’ll bring to our integrated project management team,” said Amtrak Assistant VP Luigi Rosa, who is leading the program. “We look forward to introducing some of these new team members at a future community meeting.”

Milestones, What’s Next?

The announcement follows soon after Amtrak awarded a CMAR contract to build the new Frederick Douglass Tunnel in February. And last fall, Amtrak awarded demolition contracts and a CMAR contract for the Program’s “Southern Approach,” which includes a new ADA-accessible West Baltimore MARC Station, replacing multiple bridges, and constructing tracks and other railroad infrastructure.

Early work on the program began in 2023, with demolition currently underway and major construction slated to begin later this year, including utility relocations and work for the first of five bridges.

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →