New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

September 16, 2026
A New York MTA subway car with an open gangway

With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.

Credit:

Marc A. Hermann

3 min to read


  • The MTA is moving forward with the final construction contract for Phase 2 of the Second Avenue Subway, aimed at extending the Q service to 125 St in East Harlem.
  • A Request for Proposals will be issued to qualified contractors by the end of the year with work on the largest contract, including station infrastructure and tracks, expected to start in 2027.
  • Funded by congestion relief revenue and $3.4 billion in federal aid, Phase 2's completion is targeted for fall 2032, completing the $6.968 billion project.

*Summarized by AI

New York’s Metropolitan Transportation Authority (MTA) is advancing the fourth and final construction contract for Phase 2 of the Second Avenue Subway, marking a major milestone toward completing the extension of Q service to 125 St in East Harlem.

After this Request for Qualifications (RFQ), the MTA plans to issue a Request for Proposals to qualified contractors by the end of the year and expects to select a contractor in mid-2027.

Ad Loading...

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Phase 2 of the Second Avenue Subway

With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.

After Phase 2 is completed, the Q service will run north from 96 St to 125 St and Lexington Ave, an extension of about 1.5 miles with three new stations at 106 St, 116 St, and 125 St.

In addition to providing the full systems fit-out for the three fully accessible stations at 106 St, 116 St, and 125 St, and connecting tunnel segments, this fourth contract includes work to connect the new 125 St Station to the existing 125 St 4 5 6 station, and an entrance at Park Ave, one block over, enabling convenient transfers to Metro-North’s Harlem-125 St Station and M60 Select Bus Service with service to LaGuardia Airport.

Major work in this last construction contract includes:

Ad Loading...
  • Structural work: Construct entrance canopies, station platforms, and six above-ground ancillary buildings to house ventilation, mechanical, and electrical equipment, as well as space for possible ground-floor retail and community uses.
  • Mechanical, electrical and plumbing work: Install HVAC, smoke management, fire protection, station and facility power, lighting, plumbing and drainage, and related systems.
  • Accessibility work: Install 22 elevators and 20 escalators across the three stations and facilities.
  • Communications and security systems work: Install public address systems, customer information screens, Help Point intercoms, Wi-Fi, radio, fire and emergency alarms, and security cameras.
  • Track, signal, and CBTC work: Install track, third rail, traction power, wayside signal equipment, train detection, communication infrastructure throughout the stations and tunnels.
  • Station finishes: Install architectural finishes, station lighting, signage and wayfinding, fare arrays, customer service facilities, and artwork.
  • Testing and commissioning work: Test, integrate, and commission all systems installed.
  • Site restoration: Complete permanent utility connections and restore streets, sidewalks, traffic signals, and other affected areas within the Phase 2 project limits.

Phase 2 Construction Progress

The first contract, awarded in January 2024, covers utility relocation work at the future 106 St Station. The project is about 60% complete and is expected to finish by summer 2027, MTA officials said.  

The second contract, awarded in September 2025, includes construction of two tunnels, rehabilitation of existing tunnels, construction of the new 116 St Station box, seven shafts for future ancillary buildings and station entrances, and the structural shells for the 116 St and 125 St stations. The final design is more than 50% complete. The tunnel boring machine (TBM) is currently under construction, and crews are preparing the TBM launch site for excavation. Excavation of the 125 St entrance shaft has also begun. The contract is forecast to reach substantial completion in September 2029.

The third contract, awarded in April 2026, includes excavation and construction of the 106 St structural shell, tunnel connections, ancillary buildings and station entrances, as well as utility work. The contract is expected to reach substantial completion in the third quarter of 2030.

Quick Answers

The fourth construction contract aims to complete the extension of Q service to 125 St in East Harlem by constructing station infrastructure, tracks, and signals.

*Summarized by AI

Ad Loading...

More Rail

A rendering of Trinity Metro's future station at the Medical Center
Rail•by Alex Roman•October 30, 2026

Trinity Metro Breaks Ground on $270M TEXRail Extension

The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.

Read More →
Austin Light Rail rendering from UT perspective
Rail•by Alex Roman•October 30, 2026

Bringing Austin’s First Light Rail System to Life

Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.

Read More →
Two Metra locomotives on rail tracks.
Rail•by Alex Roman•October 29, 2026

Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail

The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.

Read More →
Ad Loading...
METRO Magazine graphic featuring railroad tracks and switches inside a dark tunnel with the headline “Amtrak Completes First Street Tunnel Upgrades, Restores Service.”
Rail•by Elora Haynes•October 29, 2026

Amtrak Completes First Street Tunnel Upgrades, Restores Service

The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.

Read More →
FRA Invests $2.3B in Rail Projects Nationwide
Rail•by Alex Roman•October 28, 2026

FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide

The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.

Read More →
A Caltrain electric railcar on the tracks
Rail•by Alex Roman•October 27, 2026

Caltrain’s Electrification Drives a New Era of Ridership Growth

The railroad’s shift to electric service has brought more frequent trains, stronger customer satisfaction, and increased ridership, earning it APTA’s Outstanding Public Transportation System award.

Read More →
Ad Loading...
METRO Magazine graphic featuring a dark blue background with abstract curved lines and the headline “FTA Advances $164M Broward County Commuter Rail Project.”
Rail•by Staff and News Reports•October 26, 2026

FTA Advances $164M Broward County Commuter Rail Project

The proposed 10.5-mile commuter rail extension would connect Fort Lauderdale and Aventura, expanding passenger rail options in South Florida.

Read More →
An A line MTA subway car near the soon to be replaced signaling system.
Rail•by Staff and News Reports•October 23, 2026

New York MTA Launches Historic $1.9B Signal, Track Modernization Project

Funded in part by congestion pricing revenue, the project will replace nearly century-old signals along the A and C lines in Brooklyn and Queens.

Read More →
The LA Metro San Fernando Valley light rail extension corridor
Rail•by Alex Roman•October 20, 2026

LA Metro Breaks Ground on East San Fernando Valley Light Rail Project

The 6.7-mile line will add 11 stations along Van Nuys Boulevard, expand access to jobs and regional transit connections, and support Metro’s broader efforts to improve mobility as rail ridership grows.

Read More →
Ad Loading...
New Standard Helps Transit Agencies Address Climate Risks
Security and Safety•by Alex Roman•October 19, 2026

CSA Group Releases Climate Resilience Standard for Transit, Passenger Rail

Developed with support from the Standards Council of Canada, CSA D700 guides assessing climate-related risks and planning adaptation measures for transit and passenger rail systems.

Read More →