New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.
Marc A. Hermann
- The MTA is moving forward with the final construction contract for Phase 2 of the Second Avenue Subway, aimed at extending the Q service to 125 St in East Harlem.
- A Request for Proposals will be issued to qualified contractors by the end of the year with work on the largest contract, including station infrastructure and tracks, expected to start in 2027.
- Funded by congestion relief revenue and $3.4 billion in federal aid, Phase 2's completion is targeted for fall 2032, completing the $6.968 billion project.
*Summarized by AI
New York’s Metropolitan Transportation Authority (MTA) is advancing the fourth and final construction contract for Phase 2 of the Second Avenue Subway, marking a major milestone toward completing the extension of Q service to 125 St in East Harlem.
After this Request for Qualifications (RFQ), the MTA plans to issue a Request for Proposals to qualified contractors by the end of the year and expects to select a contractor in mid-2027.
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Phase 2 of the Second Avenue Subway
With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.
After Phase 2 is completed, the Q service will run north from 96 St to 125 St and Lexington Ave, an extension of about 1.5 miles with three new stations at 106 St, 116 St, and 125 St.
In addition to providing the full systems fit-out for the three fully accessible stations at 106 St, 116 St, and 125 St, and connecting tunnel segments, this fourth contract includes work to connect the new 125 St Station to the existing 125 St 4 5 6 station, and an entrance at Park Ave, one block over, enabling convenient transfers to Metro-North’s Harlem-125 St Station and M60 Select Bus Service with service to LaGuardia Airport.
Major work in this last construction contract includes:
- Structural work: Construct entrance canopies, station platforms, and six above-ground ancillary buildings to house ventilation, mechanical, and electrical equipment, as well as space for possible ground-floor retail and community uses.
- Mechanical, electrical and plumbing work: Install HVAC, smoke management, fire protection, station and facility power, lighting, plumbing and drainage, and related systems.
- Accessibility work: Install 22 elevators and 20 escalators across the three stations and facilities.
- Communications and security systems work: Install public address systems, customer information screens, Help Point intercoms, Wi-Fi, radio, fire and emergency alarms, and security cameras.
- Track, signal, and CBTC work: Install track, third rail, traction power, wayside signal equipment, train detection, communication infrastructure throughout the stations and tunnels.
- Station finishes: Install architectural finishes, station lighting, signage and wayfinding, fare arrays, customer service facilities, and artwork.
- Testing and commissioning work: Test, integrate, and commission all systems installed.
- Site restoration: Complete permanent utility connections and restore streets, sidewalks, traffic signals, and other affected areas within the Phase 2 project limits.
Phase 2 Construction Progress
The first contract, awarded in January 2024, covers utility relocation work at the future 106 St Station. The project is about 60% complete and is expected to finish by summer 2027, MTA officials said.
The second contract, awarded in September 2025, includes construction of two tunnels, rehabilitation of existing tunnels, construction of the new 116 St Station box, seven shafts for future ancillary buildings and station entrances, and the structural shells for the 116 St and 125 St stations. The final design is more than 50% complete. The tunnel boring machine (TBM) is currently under construction, and crews are preparing the TBM launch site for excavation. Excavation of the 125 St entrance shaft has also begun. The contract is forecast to reach substantial completion in September 2029.
The third contract, awarded in April 2026, includes excavation and construction of the 106 St structural shell, tunnel connections, ancillary buildings and station entrances, as well as utility work. The contract is expected to reach substantial completion in the third quarter of 2030.
Quick Answers
The fourth construction contract aims to complete the extension of Q service to 125 St in East Harlem by constructing station infrastructure, tracks, and signals.
*Summarized by AI
More Rail

First Full MetroLink Rail Expansion Completed in 20 Years with $192M Airport Project
The project links two St. Louis-area airports by light rail while adding roadway and bike trail connections to improve regional access and mobility.
Read More →
Utilimarc Launches SmartReplace to Optimize Fleet Replacement Decisions
AI-powered SmartReplace helps fleets prioritize vehicle replacements, model budget scenarios, and build more defensible long-term strategies.
Read More →
Scenes from APTA TRANSform & EXPO 2026
Transit leaders, manufacturers, and industry professionals gathered in Chicago to explore new technologies, share ideas, and discuss the future of public transportation.
Read More →
USDOT Awards $416 Million for Florida Rail Crossing Safety Upgrades, New Brightline Station
The projects aim to reduce risks for motorists and pedestrians at rail crossings while expanding passenger rail access along Florida’s Space Coast.
Read More →
OCTA Declares Emergency to Protect Rail Corridor From Coastal Erosion
The California agency is accelerating shoreline protection and plans to place approximately 690,000 cubic yards of sand along the San Clemente coast to protect a key passenger and freight rail link.
Read More →
More Than a Summer Job: Building the Next Generation of Transit Talent
The Delaware River Port Authority and PATCO have transformed their internship program into a hands-on professional development experience that introduces students to the breadth of transportation careers — and creates a pipeline for future employees.
Read More →
Airo Trains Make Their Amtrak Cascades Debut in the Pacific Northwest
Effective immediately, two cutting-edge Airo trainsets will join the Amtrak Cascades route, operating four daily trips between Vancouver, B.C., Seattle, Portland, and Eugene, Oregon, marking the first introduction of Airo trains into passenger service anywhere in the country.
Read More →
Florida's Brightline Announces Financial Restructuring
Brightline Florida says train operations will continue as normal as certain parent entities enter Chapter 11 and financial stakeholders provide $490 million in new long-term capital.
Read More →
ENC Lands MATA Contract and More in Biz Briefs
In this edition of Biz Briefs, we spotlight the latest developments shaping the future of mobility.
Read More →
Strada360’s Steve Lassey on Turning Transit Data Into Better Decisions
From breaking down data silos to preparing for AI, Strada360 CEO Steve Lassey discusses how transit agencies can use technology to improve operations, customer information, and long-term decision-making.
Read More →