New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.
Marc A. Hermann
- The MTA is moving forward with the final construction contract for Phase 2 of the Second Avenue Subway, aimed at extending the Q service to 125 St in East Harlem.
- A Request for Proposals will be issued to qualified contractors by the end of the year with work on the largest contract, including station infrastructure and tracks, expected to start in 2027.
- Funded by congestion relief revenue and $3.4 billion in federal aid, Phase 2's completion is targeted for fall 2032, completing the $6.968 billion project.
*Summarized by AI
New York’s Metropolitan Transportation Authority (MTA) is advancing the fourth and final construction contract for Phase 2 of the Second Avenue Subway, marking a major milestone toward completing the extension of Q service to 125 St in East Harlem.
After this Request for Qualifications (RFQ), the MTA plans to issue a Request for Proposals to qualified contractors by the end of the year and expects to select a contractor in mid-2027.
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Phase 2 of the Second Avenue Subway
With the first three contracts progressing concurrently, the project budgeted at $6.968 billion is expected to be fully completed by the fall of 2032. Congestion relief revenue and $3.4 billion in federal funding make the project possible.
After Phase 2 is completed, the Q service will run north from 96 St to 125 St and Lexington Ave, an extension of about 1.5 miles with three new stations at 106 St, 116 St, and 125 St.
In addition to providing the full systems fit-out for the three fully accessible stations at 106 St, 116 St, and 125 St, and connecting tunnel segments, this fourth contract includes work to connect the new 125 St Station to the existing 125 St 4 5 6 station, and an entrance at Park Ave, one block over, enabling convenient transfers to Metro-North’s Harlem-125 St Station and M60 Select Bus Service with service to LaGuardia Airport.
Major work in this last construction contract includes:
- Structural work: Construct entrance canopies, station platforms, and six above-ground ancillary buildings to house ventilation, mechanical, and electrical equipment, as well as space for possible ground-floor retail and community uses.
- Mechanical, electrical and plumbing work: Install HVAC, smoke management, fire protection, station and facility power, lighting, plumbing and drainage, and related systems.
- Accessibility work: Install 22 elevators and 20 escalators across the three stations and facilities.
- Communications and security systems work: Install public address systems, customer information screens, Help Point intercoms, Wi-Fi, radio, fire and emergency alarms, and security cameras.
- Track, signal, and CBTC work: Install track, third rail, traction power, wayside signal equipment, train detection, communication infrastructure throughout the stations and tunnels.
- Station finishes: Install architectural finishes, station lighting, signage and wayfinding, fare arrays, customer service facilities, and artwork.
- Testing and commissioning work: Test, integrate, and commission all systems installed.
- Site restoration: Complete permanent utility connections and restore streets, sidewalks, traffic signals, and other affected areas within the Phase 2 project limits.
Phase 2 Construction Progress
The first contract, awarded in January 2024, covers utility relocation work at the future 106 St Station. The project is about 60% complete and is expected to finish by summer 2027, MTA officials said.
The second contract, awarded in September 2025, includes construction of two tunnels, rehabilitation of existing tunnels, construction of the new 116 St Station box, seven shafts for future ancillary buildings and station entrances, and the structural shells for the 116 St and 125 St stations. The final design is more than 50% complete. The tunnel boring machine (TBM) is currently under construction, and crews are preparing the TBM launch site for excavation. Excavation of the 125 St entrance shaft has also begun. The contract is forecast to reach substantial completion in September 2029.
The third contract, awarded in April 2026, includes excavation and construction of the 106 St structural shell, tunnel connections, ancillary buildings and station entrances, as well as utility work. The contract is expected to reach substantial completion in the third quarter of 2030.
Quick Answers
The fourth construction contract aims to complete the extension of Q service to 125 St in East Harlem by constructing station infrastructure, tracks, and signals.
*Summarized by AI
More Rail

San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →
The Business Voice Behind Public Transportation
As chair of APTA’s Business Members Board of Governors, Ray Melleady explains how more than 850 business members are partnering with transit agencies to advance funding, innovation, and industry-wide collaboration.
Read More →