2 SacRT Siemens Light Rail Trains Hit 1K Miles of Testing
The 1,000-mile testing process is the final step of testing required to ensure all safety and quality standards are met before the train can operate on SacRT’s tracks when service of the new low-floor trains begins later this summer.

As part of SacRT’s commitment to being good stewards of the public funds it receives to improve the local transportation network, SacRT is quickly and efficiently modernizing the entire light rail system.
Photo: SacRT
The Sacramento Regional Transit District (SacRT) announced two of the 20 new S700 Siemens low-floor light rail vehicles, which have been delivered, completed 1,000 miles of testing and are officially deemed ready for passenger service.
The 1,000-mile testing process is the final step of testing required to ensure all safety and quality standards are met before the train can operate on SacRT’s tracks when service of the new low-floor trains begins later this summer.
The other 18 vehicles are currently in different phases of testing.
“Ensuring the safety and reliability of our trains is our top priority,” said SacRT GM/CEO Henry Li. “I commend our dedicated team for their hard work and commitment throughout the rigorous testing process. These new low-floor vehicles will enhance accessibility and comfort for all our passengers, and we are excited to place them in service on the Gold and Green lines later this summer.”
SacRT’s Light Rail Modernization
As part of SacRT’s commitment to being good stewards of the public funds it receives to improve the local transportation network, SacRT is quickly and efficiently modernizing the entire light rail system.
The Light Rail Modernization project is a major capital project in the Sacramento region that includes the purchase and rollout of new accessible low-floor light rail vehicles, modifications to station platforms to meet the height requirements of the new vehicles, and the addition of a passing track to allow for 15-minute frequency at all four Folsom area stations.
The first phase of station platform construction on the Gold Line is nearly complete, and SacRT will begin phase two of construction on Blue Line stations this fall.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →