Amtrak Awards Contract to Build New Connecticut River Bridge

The milestone comes on the heels of recent permit approvals from the U.S. Army Corps of Engineers and Connecticut Department of Energy and Environmental Protection.

June 29, 2024
Amtrak Awards Contract to Build New Connecticut River Bridge

The new Connecticut River Bridge will improve reliability and reduce delays for Amtrak’s intercity services, Connecticut Shore Line East commuter service, and freight operators along the Northeast Corridor, America’s busiest rail corridor.

Photo: Amtrak

2 min to read


Amtrak will soon begin construction of a new, modern Connecticut River Bridge to replace the existing bridge following the award of a construction contract to O&G/Tutor Perini, a Joint Venture.

The milestone comes on the heels of recent permit approvals from the U.S. Army Corps of Engineers and Connecticut Department of Energy and Environmental Protection.

Ad Loading...

The Connecticut River Bridge

The new Connecticut River Bridge will improve reliability and reduce delays for Amtrak’s intercity services, Connecticut Shore Line East commuter service, and freight operators along the Northeast Corridor (NEC), America’s busiest rail corridor.

The Connecticut River Bridge is one of several passenger rail improvement projects in the State of Connecticut, including the Connecticut Department of Transportation’s Devon Bridge and Walk Bridge replacement projects, among others.

“Today’s milestone brings us one step closer to putting shovels in the ground and kicking off construction for this major project,” said Amtrak CEO Stephen Gardner.

Amtrak will construct a new two-track bridge to replace the existing two-track Connecticut River Bridge between Old Saybrook and Old Lyme, Conn. — roughly midway between New York City and Providence, R.I.

The new moveable bridge will be located immediately south of the existing moveable bridge, featuring modern track, signal, catenary, power, communication, and other supporting rail infrastructure.

Ad Loading...

It is designed with a maximum operating speed of 70 mph, a 55% increase from today’s maximum speed of 45 mph.

Maritime navigation and safety will also improve due to additional vertical clearance compared with the existing bridge.

Funding for the Project

The project is being delivered through a Design-Bid-Build contract. The design is 100% complete and construction is set to begin in late summer/early fall 2024.

Amtrak also previously awarded a construction management (CM) contract to AECOM, who will assist Amtrak with management of the construction contractor, document control, schedule and budget oversight, and community outreach support. This team will be fully integrated with Amtrak’s in-house Capital Delivery department and the construction contractor.

The approximately $1.3 billion project is primarily funded by the Infrastructure Investment & Jobs Act (IIJA), thanks to a $826.64 million federal grant awarded by FRA. The remaining portion will be funded by Amtrak and the State of Connecticut.

Ad Loading...

The project is key to Amtrak’s new era of passenger rail, which includes investments into modern trains, stations, tunnels, bridges, and other critical infrastructure upgrades to enhance the customer experience, improve safety and reliability, and expand capacity to serve more future customers.

More Rail

Operation Lifesaver Rail Safety Education logo over railroad tracks background, representing rail safety awareness initiatives.
Railby News/Media ReleaseMay 4, 2026

Operation Lifesaver Awards Rail Safety Outreach Funds in 12 States

Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.

Read More →
Caltrain trains on tracks
Railby StaffMay 1, 2026

Caltrain Survey Shows Record-High Rider Approval

The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
Ad Loading...
Carmen C. Cham of HNTB
Managementby Alex RomanApril 29, 2026

How Transit Architecture Is Reshaping the Rider Journey

In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.

Read More →
A Red Line Rendering
Railby StaffApril 27, 2026

Chicago Kicks Off Historic Red Line Extension at Michigan Avenue Station Site

The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.

Read More →
Trains at railroad crossings
Security and Safetyby StaffApril 27, 2026

USDOT Invests $1.1B to Enhance Safety Infrastructure at Railroad Crossings

Every year, more than 2,000 incidents and 300 fatalities occur at railroad crossings nationwide. 

Read More →
Ad Loading...
Siemens and LK Comstock photo for Fulton-Liberty Lines
Security and Safetyby StaffApril 27, 2026

NYC’s Fulton–Liberty Lines Get Digital Signal Upgrade from Siemens and L.K. Comstock

The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.

Read More →
WMATA 7000-series railcars at Navy Yard
Managementby StaffApril 24, 2026

WMATA Adopts FY2027 Budget, Boosts Service Without Raising Fares

While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.

Read More →
Denver RTD's A Line with passengers
Railby StaffApril 23, 2026

Denver's RTD Celebrates 10th Anniversary of the A Line

With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.

Read More →
Ad Loading...
Passengers on a public transit vehicle.
Railby StaffApril 21, 2026

Virginia DRPT Releases Draft Six-Year Program for Transit, Rail Investments

The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.

Read More →