Chicago Transit completes rail expansion project

Platforms at 16 stations were extended to provide space for eight-car trains resulting in a one-third increase in capacity over the six-car configuration. Eight-car train operation began on March 30, 2008.

January 11, 2010
2 min to read


The Chicago Transit Authority (CTA) celebrated the completion of 18 station renovations as part of the agency's $530 million Brown Line Capacity Expansion Project.

Belmont and Fullerton — the final two stations to complete construction — were rebuilt in the same locations and now include elevators for customers with disabilities making 91 of the CTA's 144 rail stations now accessible. CTA preserved the two historic stationhouses at each station and relocated them across the street to serve as secondary entrances.

Ad Loading...

On Saturday, Mayor Richard M. Daley, Chicago Transit Board Chairman Terry Peterson and CTA President Richard L. Rodriguez joined federal, state and city officials at the Fullerton rail station for a ribbon cutting ceremony celebrating the project completion.

 

The Brown Line Capacity Expansion Project was designed to relieve congestion, provide for future growth by increasing capacity, and improve service delivery, safety and customer comfort. The project also made the Brown Line accessible to all CTA customers, in accordance with the Americans with Disabilities Act (ADA) guidelines.

As part of the expansion project, platforms at 16 stations were extended to provide space for eight-car trains resulting in a one-third increase in capacity over the six-car configuration. Eight-car train operation began on March 30, 2008.

In addition to station renovations, the Brown Line Capacity Expansion Project included building a new substation and rehabilitating an existing substation to supply the additional power needed to power eight-car trains; installation of a new signal system at Clark Junction — the location where Brown, Red and Purple Express trains merge just north of the Belmont station; and the rehabilitation of the Clark Tower facility at the junction.

Funding for the Brown Line capacity expansion project was made possible through a combination of federal and non-federal funds. In 2004, the CTA was the recipient of a federal Full Funding Agreement Grant totaling $245.52 million.

 

More Rail

A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →
Ad Loading...
World Cup Crowds Will Test Transit Systems
ManagementJune 3, 2026

When Routine Fails: How Public Transit Must Adapt for the World Cup

The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.

Read More →
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 2, 2026

California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract

The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.

Read More →
Sound Transit Sounder train
Railby StaffJune 2, 2026

Seattle's Sound Transit Launches New Sounder Railcars into Service

Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.

Read More →
Ad Loading...
Railby StaffJune 2, 2026

Alstom Partners With Universities to Build Rail Talent Pipeline

The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.

Read More →
Managementby StaffJune 1, 2026

Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin

Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.

Read More →
Managementby StaffMay 29, 2026

Seattle’s Sound Transit Adopts Updated ST3 System Plan

The updated system plan incorporates cost savings across the agency, including new revenue sources and financial policies, to set the agency on a sustainable path for the future.

Read More →
Ad Loading...
An EMBARK bus going down the street.
Managementby Alex RomanMay 28, 2026

Inside Look: EMBARK Expands Fare-Free Transit Program Through New Public-Private Partnership

The OKC transit agency says sponsorship helps subsidize the Third Friday Free initiative while reducing barriers for first-time riders and boosting ridership across buses, streetcars, and river cruises.

Read More →