Denver RTD marks Eagle P3's halfway point
The three lines are the East Rail Line to Denver International Airport, the Gold Line to Arvada and Wheat Ridge, and the first segment of the Northwest Rail Line to south Westminster.
The Denver Regional Transportation District’s (RTD) Eagle P3 project, which comprises three commuter rail lines and a commuter rail maintenance facility, reached the halfway-to-completion point.
The three lines are the East Rail Line to Denver International Airport (DIA), the Gold Line to Arvada and Wheat Ridge, and the first segment of the Northwest Rail Line to south Westminster.
The three lines and the maintenance facility will open in 2016.
The Eagle P3 project is the nation’s first full public-private partnership for transit. Local RTD taxes combine with a $1.03 billion federal grant and $450 million from Denver Transit Partners, the 34-year concessionaire that will build, operate and maintain the trains, to make up the $2.2 billion project.
In addition to East and Gold, Eagle is building the first six-mile segment of Northwest Rail Line to Westminster. That became possible because the first four miles are shared with the Gold Line. In all, the project will add 36 miles of rail service to the metro area.
FasTracks is RTD’s voter-approved transit expansion program to build 122 miles of commuter rail and light rail, 18 miles of bus rapid transit service, add 21,000 new parking spaces, redevelop Denver Union Station and redirect bus service to better connect the eight-county district.
More Rail

FTA Ends Direct Oversight of MBTA Safety Actions
The federal agency closed its remaining special directive to the Massachusetts Department of Public Utilities following a safety review that began in 2022.
Read More →
Amtrak, CN Reach Agreements to Strengthen Passenger Rail Service, Safety
The agreement resolves a more than decade-long proceeding before the Surface Transportation Board concerning the terms and conditions for Amtrak services, such as the City of New Orleans, Illini/Saluki, and Wolverine.
Read More →
New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →