Related: Metrolink launches first version of mobile ticketing app
Metrolink files suit against its railcar manufacturer
The suit, which was filed in Los Angeles Superior Court in the wake of a Metrolink train that derailed in Oxnard last year, alleges breach of contract and breach of warranty and seeks unspecified damages from Hyundai Rotem Co.


LOS ANGELES — Metrolink filed a suit against the maker of its passenger railcars, Hyundai Rotem Co., alleging they had faulty parts that failed to keep trains on the track in an accident, NBC LA reports.
The suit, which was filed in Los Angeles Superior Court in the wake of a Metrolink train that derailed in Oxnard last year, alleges breach of contract and breach of warranty and seeks unspecified damages.
According to the lawsuit, in 2005 Metrolink issued a "request for proposal" for railcars with state-of-the-art technology designed to protect passengers if a collision occurred. Ultimately, Metrolink claims it chose to go Hyundai “based in large part on its purported experience and expertise in designing and manufacturing safe railcars." For the full story, click here.
More Rail

Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →
Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet
The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.
Read More →
When Routine Fails: How Public Transit Must Adapt for the World Cup
The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.
Read More →
California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract
The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.
Read More →
Seattle's Sound Transit Launches New Sounder Railcars into Service
Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.
Read More →