Report Recommends Extending Silver Line in Boston

Opening in 2018, the SL3 connects Chelsea with Logan Airport, East Boston, the Seaport District, and South Station, making quick, easy connections to many area bus routes, the Blue Line, the Red Line, and the Commuter Rail.

Report Recommends Extending Silver Line in Boston

The SLXAA’s recommended extension to Sullivan Square would continue SL3 service through Everett and into Boston, connecting Chelsea directly with the Orange Line and a dozen more MBTA bus routes.

Photo: MBTA

2 min to read


The MBTA and the Massachusetts Department of Transportation (MassDOT) released the results of the Silver Line Extension Alternatives Analysis (SLXAA), which recommends extending Silver Line 3 (SL3) service from its current terminus in Chelsea to Sullivan Square Station on the Orange Line.

“Extending the SL3 to Sullivan Square will have a profound impact on thousands of riders, expanding access to our rapid transit system and a dozen more bus routes, amplifying more opportunities for jobs, education, and recreational activities,” said MBTA GM/CEO Phillip Eng. “We appreciate the efforts of the MBTA team and our partners at MassDOT for their work on the Silver Line Extension Alternatives Analysis and look forward to reviewing the upcoming design.”

Ad Loading...

MBTA’s SL3

Opening in 2018, the SL3 connects Chelsea with Logan Airport, East Boston, the Seaport District, and South Station, making quick, easy connections to many area bus routes, the Blue Line, the Red Line, and the Commuter Rail.

The SLXAA’s recommended extension to Sullivan Square would continue SL3 service through Everett and into Boston, connecting Chelsea directly with the Orange Line and a dozen more MBTA bus routes.

Approximately 80% of the six-mile-long extension through Chelsea, Everett, and Boston includes exclusive bus-only lanes, with the SL3 serving eight new stations. Bus routes that already operate in these areas would also have the added benefit of operating within these dedicated bus-only lanes for faster travel times outside of mixed traffic.

By extending SL3 service to Sullivan Square, Chelsea, and Everett, residents will benefit from increased service frequency outside of traditional morning and evening peak commuting hours and expanded access to 345,000 jobs via a 45-minute transit commute. Extending the SL3 is projected to increase daily SL3 ridership by over 15,000 riders.

The SLXAA also included an analysis of extending the SL3 beyond the Orange Line to Kendall Square or downtown Boston, ultimately determining further study is required. Extending the SL3 to these locations would also require the MBTA to further expand its Silver Line vehicle fleet and maintenance facilities.

Ad Loading...

In the near-term, the MBTA’s Bus Network Redesign team plans to implement high-frequency bus service from Chelsea to the Orange Line and from Sullivan Square to Kendall Square, creating multiple new connections in service.

Next Steps

The MBTA and MassDOT partnered with area municipalities to determine the potential alternatives and benefits of extending the SL3, and the SLXAA follows previous recommendations by the Lower Mystic Regional Working Group and the Everett Transit Action Plan.

Following the release of the SLXAA, the MBTA and MassDOT are exploring funding opportunities to advance the SLX design and engineering phase.

The preliminary cost to extend the SL3, including all associated roadway reconstruction, is anticipated to be approximately $95 million.

More Bus

Cover Photo for Bus Tech Talk
ManagementApril 9, 2026

Bus Tech Talk: AC Transit’s Cecil Blandon on Leadership, Mentorship, and a Career in Transit

In Part 1, Blandon shares his journey from the U.S. Marines to a leadership role in public transit, along with insights on mentorship and professional growth within the industry.

Read More →
A blurry TransLink R2 rapid bus
Managementby StaffApril 8, 2026

Vancouver's TransLink Fast-Tracks RapidBus Line to Metrotown

Funded through the 2025 Investment Plan, the new R2 Marine–Willingdon RapidBus is expected to begin service in September, more than three months ahead of schedule.

Read More →
Complete Parts logo
Busby StaffApril 1, 2026

Complete Coach Works Unveils Reimagined Parts Department with Expanded Capabilities

Complete Parts features new branding with a new logo, a new contact telephone number, a dedicated order desk, enhanced processes and inventory, all designed to provide the parts bus operations need.  

Read More →
Ad Loading...
frontrunner bus
SponsoredApril 1, 2026

Breaking Accessibility Barriers with the Low Floor Frontrunner Minibus

Accessible transit isn’t a feature—it’s a responsibility. This whitepaper explores how the Low-Floor Frontrunner is redefining mobility with a breakthrough design that removes barriers, empowers riders, and delivers measurable operational advantages for agencies. Discover why this next generation minibus is setting a new standard for inclusive transportation.

Read More →
A shot of ENC's manufacturing facility
Busby StaffMarch 31, 2026

ENC Named 'Partner of Choice' to Support Philadelphia SEPTA’s $43M FTA Grant

SEPTA was awarded $43 million in competitive grant funding from the FTA's FY25 Low and No Emission and Bus and Bus Facilities grant programs to support this procurement.

Read More →
Cover photo for Bus Tech Talk with Cecil Blandon
Managementby Alex RomanMarch 27, 2026

AC Transit’s Cecil Blandon on Leadership, Mentorship, and a Career in Transit

In part 1 of a two-part conversation, AC Transit’s director of maintenance joins co-hosts Alex Roman and Mark Hollenbeck to discuss his journey from the U.S. Marines to public transit and the role mentorship plays in developing the next generation of industry leaders.

Read More →
Ad Loading...
An MBTA bus with a passenger boarding at shelter.
Busby StaffMarch 27, 2026

MBTA Confirms Funding for Upgraded Arborway Bus Facility

When construction is complete, battery-electric buses will operate from the Arborway facility on Day One, providing cleaner, quieter, and more reliable service for riders, the MBTA said. After completion, the old facility will be demolished, and the land will be made available for redevelopment.

Read More →
Nadine S. Lee
Managementby StaffMarch 26, 2026

DART's President/CEO Announces Departure from Agency

Nadine S. Lee, who has served as president/CEO since July 2021, said the decision comes after careful reflection on the agency’s progress and its path forward.

Read More →
Assemblywoman Castillo and ENC officials at California facility.
Busby StaffMarch 23, 2026

ENC Hosts California Assemblywoman, Celebrates American Manufacturing and Economic Growth

The visit underscored ENC's role as a major employer in Assembly District 58 and its commitment to American manufacturing and skilled local jobs.

Read More →
Ad Loading...
Cover of METROspectives episode with The Bus Coalition
BusMarch 20, 2026

Inside The Bus Coalition’s Push for Stronger Federal Transit Investment

In this conversation, TBC’s Executive Director Ed Redfern, President Corey Aldridge, and Washington Representative Joel Rubin outline the coalition’s key policy priorities, the challenges facing transit agencies, and how industry stakeholders can work together to strengthen the voice of bus transit at the federal level.

Read More →