WMATA's Red Line to Open Early, Under Budget
With the Red Line work completed, the weekend will be free of any scheduled track work going into New Year's Eve when train service systemwide will be extended to 2 a.m. to accommodate workers and revelers ringing in the new year.

Service on the Red Line has been suspended since Dec. 18, to repair the deteriorating concrete beams and ceiling that date to the system’s original construction.
Photo: WMATA
The Washington Metropolitan Area Transit Authority (WMATA) announced Red Line construction between the Dupont Circle and Gallery Place stations will be completed early and $250,000 under budget, following construction for critical tunnel repairs and infrastructure upgrades, with normal Red Line services re-launching Dec. 30.
With the Red Line work completed, the weekend will be free of any scheduled track work going into New Year's Eve when train service systemwide will be extended to 2 a.m. to accommodate workers and revelers ringing in the new year.
In addition, 24/7 DC bus service is now available on 14 routes for those in the District traveling after the rail system closes.
Red Line Service
Service on the Red Line has been suspended since Dec. 18, to repair the deteriorating concrete beams and ceiling that date to the system’s original construction. Additionally, the work zone was extended Dec. 22 to 24 with no Red Line service between Gallery Place and Union Station.
Free shuttle buses replaced trains during construction, providing more than 172,000 passenger trips to date between the affected stations.
"We appreciate all of our customers, businesses, the District and the effort our Metro staff who worked through the holidays to get this critical work done," said WMATA GM/CEO Randy Clarke. “Maintaining the safety and reliability of the system is vital. Thanks to Mayor Bowser and the District Department of Transportation, we were able to use special dedicated bus lanes created for this project to minimize the impact to customers.”
Construction Highlights
Red Line construction highlights included:
WMATA’s construction team used more than eight tons of concrete and 466 pounds of rebar to rebuild the Red Line tunnel ceiling to prevent concrete from falling onto trains.
The team replaced 3,159 linear feet of running rail between Farragut North and Metro Center.
Workers installed 1,152 lights for the new platform edge lighting between Farragut North and Judiciary Sq with brighter, more sustainable LED lights.
Added extra insulation to the third rail power cables between Gallery Place and Judiciary Square to provide a moisture barrier of the electrified third rail, which powers the trains.
To prepare for its next generation train signaling system, Metro installed 15,914 linear feet of fiber optic cables between Farragut North and Judiciary Sq.
The Red Line construction is part of WMATA's 10-year, $15 billion Capital Improvement Program, investing in system safety, reliability, and the region's economy. The capital program will improve the customer experience and keep the region's infrastructure in a state of good repair.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →