San Francisco tunnel boring continues progress

Beginning Tuesday, Big Alma was set to be in operation 24 hours a day to build the approximately 425 feet of new tunnel beneath the Market Street tunnels.

January 29, 2014
2 min to read


The San Francisco Municipal Transportation Agency (SFMTA) announced the Central Subway’s second tunnel boring machine (TBM) will soon pass beneath existing Bay Area Rapid Transit District (BART) and Muni Metro tunnels, while passing under Market Street from SoMa into Union Square.

When the Central Subway opens, the new tunnels will allow T Third Line trains to cut travel times by more than half along this busy corridor.

Ad Loading...

The SFMTA has worked in close coordination with BART and an independent panel of top tunneling experts to plan and carry out this key phase of tunnel construction. To pass beneath Market Street and the existing transit tunnels, TBM Big Alma will turn slightly left beneath 4th Street just south of Market Street. The machine will then veer right to head north under Market Street and then Stockton Street. The new T Third Line tunnels will be about 10 feet below the existing BART tunnels.

Beginning Tuesday, Big Alma was set to be in operation 24 hours a day to build the approximately 425 feet of new tunnel beneath the Market Street tunnels. Late last year the first TBM, called Mom Chung, safely and successfully completed the same undercrossing, using the same techniques and interagency coordination. Mom Chung is now beginning to tunnel under Nob Hill, heading toward Chinatown.

Including both tunnels, tunneling contractor Barnard Impregilo Healy (BIH) has constructed more than 6,900 feet of tunnel under 4th Street and Stockton Street so far.

The crossing under BART may last up to six days, with the tunneling also possibly causing BART to run at slower speeds in the area.

More Rail

A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Ad Loading...
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →
Ad Loading...
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →
World Cup Crowds Will Test Transit Systems
ManagementJune 3, 2026

When Routine Fails: How Public Transit Must Adapt for the World Cup

The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.

Read More →
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 2, 2026

California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract

The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.

Read More →
Ad Loading...
Sound Transit Sounder train
Railby StaffJune 2, 2026

Seattle's Sound Transit Launches New Sounder Railcars into Service

Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.

Read More →