Sound Transit Sets Schedule for Stride BRT

Sound Transit expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Sound Transit Sets Schedule for Stride BRT

There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3.

Photo: Sound Transit

3 min to read


The Sound Transit Board adopted a final budget and schedule for the new Stride bus rapid transit (BRT) service, including a new bus base and BRT lines on SR 522/NE 145th Street and I- 405.

Sound Transit said it expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Ad Loading...

BRT was part of Sound Transit’s 2016 voter-approved system expansion program ST3. Stride will provide high-capacity transit service with connections to light rail in Bellevue, Tukwila, Shoreline, and Lynnwood. 

When Stride begins operating, trips between Bellevue and Burien will take approximately 40 minutes; trips between Lynnwood and Bellevue will take approximately 35 minutes; and trips between Shoreline and Bothell will take approximately 37 minutes.

These travel times are an average of 20 minutes faster than the current ST Express bus service in these areas. 

“Today’s action is a significant step forward in expanding and connecting our regional high-capacity transit network,” said Sound Transit Board chair Dow Constantine. “Stride will provide fast, frequent reliable service to thousands of riders on the I-405 and SR 522 corridors, and seamless connections to Link light rail and regional bus services. We look forward to beginning construction on these BRT projects.”

The Stride project includes the Bus Base North, and BRT lines between Lynnwood and Burien on I-405, I-5, and SR 518 (S1 and S2), and between Shoreline and Bothell on SR 522/NE 145th (S3). The combined budget for the Stride BRT program is $2.35 billion.

Ad Loading...

This total budget exceeds the re-alignment cost estimate as assumed in the financial plan by approximately 14%. Factors contributing to additional costs include inflation, market factors, scope changes, and schedule impacts. 

Bus Base North (BBN)

The Bus Base North will be the first Sound Transit bus operations and maintenance base, serving the full Stride BRT fleet and a portion of the ST Express fleet, with a total capacity of 120 buses.

The operating facility will provide storage, maintenance, charging, fueling, washing, repairs, and deployment of the bus fleet. 

The Stride bus fleet will include Sound Transit's first battery-electric buses, for a cleaner, more sustainable way to travel in the region. There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3. Coaches will be in operation most of the day, charging each time they lay over at route termini.

The BBN is expected to open for service in the fourth quarter of 2027. The approved budget for the Bus Base North is $499.5 million.

Ad Loading...

I-405 Stride Bus Rapid Transit

The I-405 BRT project will establish a BRT system from the Lynnwood Transit Center to the Burien Transit Center via I-5, I-405, and SR 518.

The project consists of several elements, including new and upgraded transit centers, limited new park-and-ride capacity, freeway BRT stations, and non-motorized access improvements to the stations.

Sound Transit components that are within WSDOT’s Brickyard to SR 527 Improvement Project are part of the I-405 BRT north line (S2).

The I-405 BRT will connect to the regional transit system at three Link light rail stations and the SR 522/NE 145th BRT line.

The Stride S1 line between Burien and Bellevue is expected to open in the third quarter of 2028, and the Stride S2 line between Lynnwood and Bellevue is expected to open in the second quarter of 2029.

Ad Loading...

The approved budget for the I-405 BRT project is $1.27 billion. 

SR 522/NE 145th Street Stride Bus Rapid Transit

The SR 522/NE 145th BRT Project establishes BRT service along the corridor, primarily operating in business access and transit (BAT) and bus queue bypass lanes for nine miles between Shoreline and Bothell, with separate, connecting service options to Woodinville. The Stride S3 line is expected to open in the second quarter of 2028.

The approved budget for the SR 522/NE 145th Street BRT project is $581.5 million.

More Bus

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
King County Metro electric buses made by GILLIG.
Busby StaffJanuary 30, 2026

Seattle's King County Metro Introduces New Battery-Electric Buses

Rolling out in electric yellow and seafoam blue, the first battery-electric buses purchased from GILLIG will begin serving riders in south King County on February 2.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Ad Loading...
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Busby StaffJanuary 28, 2026

New Orleans RTA Reaches Agreement with ATU

The agreement provides competitive wages and reflects strong labor-management collaboration, positive working relationships, and a shared commitment to building a world-class transit system for the community, said RTA CEO Lona Edwards Hankins.

Read More →
Two ABQ RIDE busses at an intersection by Gold street in front of a parking structure.
Busby StaffJanuary 27, 2026

ABQ RIDE Launches Campaign to Bring Riders Back to the Bus

A new citywide campaign highlights free fares, improved service, and major upgrades to Albuquerque’s bus system.

Read More →
Ad Loading...
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Security and SafetyJanuary 22, 2026

Researchers Identify Top Risk Factors for Pedestrian-vehicle Crashes at Massachusetts Bus Stops

While their comprehensive analysis of bus stops focused on Massachusetts, the researchers are excited about the generalizability of the findings and application to other locations.

Read More →
Ad Loading...
ManagementJanuary 22, 2026

Florida's JTA Unveils Mobility Visioning Plan 2050 at State of the Authority Event

CEO Nat Ford’s address offered a look at highlights from 2025, with a focus on the future and the innovative ways the JTA is shaping mobility in Northeast Florida.

Read More →