Read More: USDOT to Help Improve Sound Transit System
Sound Transit Sets Schedule for Stride BRT
Sound Transit expects to begin construction of some project elements this year and to open for service between 2027 and 2029.

There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3.
Photo: Sound Transit
The Sound Transit Board adopted a final budget and schedule for the new Stride bus rapid transit (BRT) service, including a new bus base and BRT lines on SR 522/NE 145th Street and I- 405.
Sound Transit said it expects to begin construction of some project elements this year and to open for service between 2027 and 2029.
BRT was part of Sound Transit’s 2016 voter-approved system expansion program ST3. Stride will provide high-capacity transit service with connections to light rail in Bellevue, Tukwila, Shoreline, and Lynnwood.
When Stride begins operating, trips between Bellevue and Burien will take approximately 40 minutes; trips between Lynnwood and Bellevue will take approximately 35 minutes; and trips between Shoreline and Bothell will take approximately 37 minutes.
These travel times are an average of 20 minutes faster than the current ST Express bus service in these areas.
“Today’s action is a significant step forward in expanding and connecting our regional high-capacity transit network,” said Sound Transit Board chair Dow Constantine. “Stride will provide fast, frequent reliable service to thousands of riders on the I-405 and SR 522 corridors, and seamless connections to Link light rail and regional bus services. We look forward to beginning construction on these BRT projects.”
The Stride project includes the Bus Base North, and BRT lines between Lynnwood and Burien on I-405, I-5, and SR 518 (S1 and S2), and between Shoreline and Bothell on SR 522/NE 145th (S3). The combined budget for the Stride BRT program is $2.35 billion.
This total budget exceeds the re-alignment cost estimate as assumed in the financial plan by approximately 14%. Factors contributing to additional costs include inflation, market factors, scope changes, and schedule impacts.
Bus Base North (BBN)
The Bus Base North will be the first Sound Transit bus operations and maintenance base, serving the full Stride BRT fleet and a portion of the ST Express fleet, with a total capacity of 120 buses.
The operating facility will provide storage, maintenance, charging, fueling, washing, repairs, and deployment of the bus fleet.
The Stride bus fleet will include Sound Transit's first battery-electric buses, for a cleaner, more sustainable way to travel in the region. There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3. Coaches will be in operation most of the day, charging each time they lay over at route termini.
The BBN is expected to open for service in the fourth quarter of 2027. The approved budget for the Bus Base North is $499.5 million.
I-405 Stride Bus Rapid Transit
The I-405 BRT project will establish a BRT system from the Lynnwood Transit Center to the Burien Transit Center via I-5, I-405, and SR 518.
The project consists of several elements, including new and upgraded transit centers, limited new park-and-ride capacity, freeway BRT stations, and non-motorized access improvements to the stations.
Sound Transit components that are within WSDOT’s Brickyard to SR 527 Improvement Project are part of the I-405 BRT north line (S2).
The I-405 BRT will connect to the regional transit system at three Link light rail stations and the SR 522/NE 145th BRT line.
The Stride S1 line between Burien and Bellevue is expected to open in the third quarter of 2028, and the Stride S2 line between Lynnwood and Bellevue is expected to open in the second quarter of 2029.
The approved budget for the I-405 BRT project is $1.27 billion.
SR 522/NE 145th Street Stride Bus Rapid Transit
The SR 522/NE 145th BRT Project establishes BRT service along the corridor, primarily operating in business access and transit (BAT) and bus queue bypass lanes for nine miles between Shoreline and Bothell, with separate, connecting service options to Woodinville. The Stride S3 line is expected to open in the second quarter of 2028.
The approved budget for the SR 522/NE 145th Street BRT project is $581.5 million.
More Bus

Washington's Pierce Transit Board Sends Transit Funding Measure to November Ballot
With the adoption of Resolution 2026-006, the measure moves to the Pierce County Auditor, giving voters in the Pierce Transit service area the decision on whether to fund an expansion of local transit service within the agency’s service area.
Read More →
New York Unveils Sweeping Plan to Modernize City Bus Service
Next Stop: Fast Buses, Better Service identifies 50 priority bus corridors for improvements across the five boroughs and launches the City’s next generation of rapid bus service along five key routes.
Read More →
CTDOT Taps STV for Electric Bus Facility Design
The firm will work with CTDOT and RVT to define the facility layout, operational requirements, and long-term flexibility for RVT’s growing electric fleet.
Read More →
Ford to Leave JTA After More Than 10 Years as CEO
He plans to continue his work advancing innovative mobility solutions to improve the quality of life in communities across the nation. He did not announce specific plans.
Read More →
Transit Leaders Push for Bus Procurement Reforms to Reduce Costs
Industry experts said reducing unnecessary bus customization and modernizing purchasing practices could help transit agencies buy more vehicles, improve reliability, and make better use of limited funding.
Read More →
Executive Order Aims to Improve Transit Access Across California
The order directs state agencies to streamline transit project delivery, improve coordination, and expand access to bus and passenger rail services across California.
Read More →
Biz Briefs: Endera Delivers to California, Safety Vision Teams with San Antonio's VIA, and More
From manufacturers and suppliers to transit agencies and motorcoach operators, these updates offer a snapshot of the projects, partnerships and business moves driving the industry forward.
Read More →
VIA's Silver Line Clears Environmental Review, Advances Toward Construction
The VIA Rapid Green Line is currently under construction, with service expected to begin in April 2028.
Read More →
Modernizing Mobility with CharterUP CEO Armir Harris
From digital transformation to evolving customer demands, CharterUP's Armir Harris offers his perspective on the transportation industry's next chapter.
Read More →
CTTC Enhances Transit Workforce Pipeline Through New Partnerships and Leadership
The group's latest initiatives focus on developing talent, expanding training opportunities and addressing workforce needs across the transit sector.
Read More →