Sound Transit Sets Schedule for Stride BRT

Sound Transit expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Sound Transit Sets Schedule for Stride BRT

There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3.

Photo: Sound Transit

3 min to read


The Sound Transit Board adopted a final budget and schedule for the new Stride bus rapid transit (BRT) service, including a new bus base and BRT lines on SR 522/NE 145th Street and I- 405.

Sound Transit said it expects to begin construction of some project elements this year and to open for service between 2027 and 2029. 

Ad Loading...

BRT was part of Sound Transit’s 2016 voter-approved system expansion program ST3. Stride will provide high-capacity transit service with connections to light rail in Bellevue, Tukwila, Shoreline, and Lynnwood. 

When Stride begins operating, trips between Bellevue and Burien will take approximately 40 minutes; trips between Lynnwood and Bellevue will take approximately 35 minutes; and trips between Shoreline and Bothell will take approximately 37 minutes.

These travel times are an average of 20 minutes faster than the current ST Express bus service in these areas. 

“Today’s action is a significant step forward in expanding and connecting our regional high-capacity transit network,” said Sound Transit Board chair Dow Constantine. “Stride will provide fast, frequent reliable service to thousands of riders on the I-405 and SR 522 corridors, and seamless connections to Link light rail and regional bus services. We look forward to beginning construction on these BRT projects.”

The Stride project includes the Bus Base North, and BRT lines between Lynnwood and Burien on I-405, I-5, and SR 518 (S1 and S2), and between Shoreline and Bothell on SR 522/NE 145th (S3). The combined budget for the Stride BRT program is $2.35 billion.

Ad Loading...

This total budget exceeds the re-alignment cost estimate as assumed in the financial plan by approximately 14%. Factors contributing to additional costs include inflation, market factors, scope changes, and schedule impacts. 

Bus Base North (BBN)

The Bus Base North will be the first Sound Transit bus operations and maintenance base, serving the full Stride BRT fleet and a portion of the ST Express fleet, with a total capacity of 120 buses.

The operating facility will provide storage, maintenance, charging, fueling, washing, repairs, and deployment of the bus fleet. 

The Stride bus fleet will include Sound Transit's first battery-electric buses, for a cleaner, more sustainable way to travel in the region. There will be a fleet of double-decker buses on S1 and S2, and 60-foot articulated buses on S3. Coaches will be in operation most of the day, charging each time they lay over at route termini.

The BBN is expected to open for service in the fourth quarter of 2027. The approved budget for the Bus Base North is $499.5 million.

Ad Loading...

I-405 Stride Bus Rapid Transit

The I-405 BRT project will establish a BRT system from the Lynnwood Transit Center to the Burien Transit Center via I-5, I-405, and SR 518.

The project consists of several elements, including new and upgraded transit centers, limited new park-and-ride capacity, freeway BRT stations, and non-motorized access improvements to the stations.

Sound Transit components that are within WSDOT’s Brickyard to SR 527 Improvement Project are part of the I-405 BRT north line (S2).

The I-405 BRT will connect to the regional transit system at three Link light rail stations and the SR 522/NE 145th BRT line.

The Stride S1 line between Burien and Bellevue is expected to open in the third quarter of 2028, and the Stride S2 line between Lynnwood and Bellevue is expected to open in the second quarter of 2029.

Ad Loading...

The approved budget for the I-405 BRT project is $1.27 billion. 

SR 522/NE 145th Street Stride Bus Rapid Transit

The SR 522/NE 145th BRT Project establishes BRT service along the corridor, primarily operating in business access and transit (BAT) and bus queue bypass lanes for nine miles between Shoreline and Bothell, with separate, connecting service options to Woodinville. The Stride S3 line is expected to open in the second quarter of 2028.

The approved budget for the SR 522/NE 145th Street BRT project is $581.5 million.

More Bus

Rendering of the upgraded Derby-Shelton Train Station
Busby StaffMay 4, 2026

CTDOT Launches Four-Station Upgrades on Waterbury Line

Construction on all four stations is beginning now and is anticipated to be completed by spring 2028.

Read More →
East Colfax BRT
Busby StaffMay 4, 2026

Denver RTD breaks ground on Aurora segment of East Colfax BRT

The beginning of the final BRT segment advances construction across all five segments, reflecting steady progress toward shorter travel times, improved accessibility, and a more dependable connection to jobs, businesses, and community destinations.

Read More →
A VIA bus
Busby StaffMay 1, 2026

San Antonio's VIA Launches Next Round of Bus Improvements

The changes are designed to reduce overall travel time, shorten wait times, and get customers to their destinations more quickly.

Read More →
Ad Loading...
Federal Reserve Bank visiting ENC
Busby StaffMay 1, 2026

Fed Leaders Highlight Growth, U.S. Manufacturing at ENC

The visit is part of the SF Fed's ongoing engagement with major employers and industries across Southern California and, more broadly, the western U.S. to better understand regional economic conditions and business outlooks.

Read More →
A person working on a bus
ManagementMay 1, 2026

Data-Driven Maintenance: Focusing Effort Where It Matters Most

Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.

Read More →
frontrunner bus
SponsoredMay 1, 2026

ADA Compliant Transit: Easier, More Dignified Travel for Every Passenger

Today’s riders—and the communities you serve—expect more from public transit. While ADA compliance is required, leading transit agencies know that true accessibility also means delivering dignity, efficiency, and a better rider experience. This whitepaper reveals why forward thinking agencies nationwide choose the Low Floor Frontrunner as their first choice for ADA compliant vehicles—setting a new standard with passenger first design, faster boarding, improved safety, and unmatched operational performance.

Read More →
Ad Loading...
Cover photo for Part 2 with Cecil Blandon
Managementby Alex RomanApril 30, 2026

Bus Tech Talk: Part 2 with AC Transit’s Cecil Blandon

In Part 2 of a two-part conversation, AC Transit’s director of maintenance joins co-hosts Alex Roman and Mark Hollenbeck to discuss his maintenance team’s work with various types of vehicle, training, augmented reality, and more.

Read More →
A Valley Metro bus
Managementby StaffApril 28, 2026

Keolis Contract Extended for Valley Metro's East Valley Fixed-Route Bus Service

Under this extension, Keolis will continue to manage and operate fixed-route bus service across the East Valley, serving communities including Tempe, Mesa, Chandler, Scottsdale, the town of Gilbert, parts of Phoenix, and the Gila River Indian Community.

Read More →
A Des Moines DART bus
Busby StaffApril 28, 2026

Iowa DART Prepares for June Bus Network Launch

The new network reflects extensive input from riders and the community through Reimagine DART on what matters most in public transit — and those priorities are reflected in the changes ahead.

Read More →
Ad Loading...
A Route 8 bus travels on Denny Way in congested traffic.
Busby StaffApril 24, 2026

Seattle Speeds up Service on Denny Way

A new bus lane project aims to improve reliability on one of King County Metro’s busiest and most congestion-prone corridors.

Read More →