New York MTA Makes Progress in Expanding Accessibility, Projects Planned for 2024

In 2023, the MTA launched expanded pilots of multiple features to improve wayfinding in subway stations.

New York MTA Makes Progress in Expanding Accessibility, Projects Planned for 2024

Within the current Capital Program, MTA Construction & Development is moving forward with ADA upgrades at nine Long Island Rail Road stations.

Photo: MTA

6 min to read


The Metropolitan Transportation Authority (MTA) announced progress made in expanding accessibility across the transit system in 2023, including the completion of multiple projects and awards for future Americans with Disabilities Act (ADA) station initiatives on the subway and bus system, Long Island Rail Road, and Metro-North Railroad.

“MTA is determined to dramatically increase the accessibility of our system, as evidenced by the incredible pace of improvements over the last few years,” said MTA Chair/CEO Janno Lieber. “More new accessible stations have been opened during the current capital program than the last three programs combined, and we will keep that momentum going into 2024.”

Ad Loading...

Progress Made in Subways

In 2023, the MTA launched expanded pilots of multiple features to improve wayfinding in subway stations including floor decals on subway platforms that indicate accessible boarding areas, as well as features for customers with visual disabilities such as tactile subway line maps and NaviLens wayfinding signage. NaviLens is an app that uses unique codes to provide audio and visual wayfinding guidance and arrival status information in more than 40 languages.

In December, the MTA replaced an entire fare array at the Sutphin Blvd-Archer Av-JFK Airport station with accessible wide-aisle fare gates following a pilot at Atlantic Av-Barclays Center and Sutphin-Archer in Spring 2023. Continuing that progress, the MTA recently released a Request for Information (RFI), taking the initial step toward secure, accessible, and modern fare gates to better meet the Authority’s goals of promoting fare compliance and improving accessibility and the overall customer experience.

In 2023, the MTA completed ADA upgrades at eight subway stations across all five boroughs and awarded packages for ADA upgrades at 16 more – including a rehabilitation of the Broadway Junction station complex.

In addition, Hoyt Street ​​23 station in Downtown Brooklyn received a brand-new elevator with costs fully covered by Macy’s. The MTA and Macy’s partnered on this project through the MTA’s Transit Oriented Development group and External Partner Program, which streamlines the MTA's work with private developers impacting stations. Macy's has committed to ensuring the elevator meets the latest MTA reliability standards—at least 96.5% availability.

Two privately funded projects under the Zoning for Accessibility program started construction in 2023: a street-to-mezzanine level elevator and entrance at Queensboro Plaza ​​​NW7 and street and platform elevators at the 57 St-6 Av ​ F Station.

Ad Loading...

The following 15 stations are anticipated to be completed in 2024:

  • 68 St-Hunter College ​6

  • Woodhaven Blvd ​​JZ

  • Westchester Sq ​6

  • Queensboro Plaza ​​​NW7

  • 6 Avenue ​L

  • 14 Street ​​FM

  • 14 Street ​​​123

  • Mosholu Parkway 4​

  • Northern Blvd ​​MR

  • 149 Street-Grand Concourse ​​25

  • 149 Street-Grand Concourse ​4

  • Beach 67 Street ​A

  • Lorimer Street ​L

  • Metropolitan Avenue ​G

  • Tremont Avenue ​​BD

The MTA plans to award contracts for additional ADA stations in 2024, subject to the availability of funding from the Central Business District Tolling Program, which will provide funding for nearly 50% of the remaining 2020-2024 MTA Capital Program. 

New elevator cabs are equipped with modern technology features, including security cameras and two-way communication systems that give riders the ability to reach MTA staff at the Operations Control Center in the event of an emergency. Customers can communicate audibly via speakers or visually using a touch screen in the elevator.

MTA's Progress with Buses

In March, the MTA announced the expansion of the Bus Open Stroller pilot program to ease the challenge of traveling with young children on local and SBS buses. Over 1,000 buses on 57 routes across all five boroughs now have one designated area for a single open stroller near the rear door. 

Ad Loading...

In July, the MTA launched a new pilot for customers who use wheelchairs to test a new automated wheelchair securement system on buses. The Quantum system allows passengers to secure themselves on the bus with the touch of a button and minimal operator assistance. 

in 2023, hundreds of new and retrofitted buses hit the streets with audio/visual Digital Information Systems (DIS), flexible flip-up seats, and wider doors and ramps, advancing MTA's progress toward making its buses more universally accessible.

The Authority also expanded automated camera enforcement to 600 buses across 80 miles of bus lanes, and secured State approval to begin enforcing blocked bus stops and double-parked vehicles in 2024.

Access-A-Ride

In 2023, Access-A-Ride changed what the MTA considers an on-time pick-up for customers. The Authority is now measuring against a 20-minute window instead of a 30-minute window. Performance has shown continuous improvement since the beginning of 2023, with nearly 90% of customers being picked up within the new pick-up window.

2023 also saw the launch of an upgraded MY AAR app and web-based booking service for AAR customers. Since the updates this spring, Access-A-Ride more than doubled the number of paratransit trips booked through the app, providing an easier and more independent trip booking and tracking option for customers.

Ad Loading...

Long Island Rail Road

Within the current Capital Program, MTA Construction & Development is moving forward with ADA upgrades at nine Long Island Rail Road stations. New elevators and upgrades are planned for Amityville, Copiague, Laurelton, Lindenhurst, Locust Manor, Massapequa Park, and St. Albans. Earlier in December, the MTA announced it would move forward with upgrades to make Hollis Station accessible as well as improve accessibility at Babylon and Forest Hills. All LIRR stations are advancing in either construction or design for ADA accessibility.

The existing accessibility components at Auburndale and Valley Stream stations will also be upgraded, including new elevators between street and platform levels, modification of canopies, and new sidewalks and curb ramps that are compliant with the Americans with Disabilities Act.

Metro-North Railroad

Metro-North is in the final phase of installing new elevators at Hartsdale, Scarsdale, and Purdy’s on the Harlem line. The work also includes benches, leaning bars, and new lighting at the overpass located in Hartsdale and Scarsdale stations.

Within the current Capital Program, MTA Construction & Development is moving forward with ADA upgrades at three Metro-North stations located in the Bronx. Completely new station platforms and amenities, and two new elevators will be installed at both Woodlawn and Williams Bridge. The Botanical Garden will also be rehabilitated, and the station elevators will be upgraded.

Bridges and Tunnels

MTA Bridges and Tunnels has leveraged MTA’s infrastructure assets to promote walking and cycling and enhance safety across the region. So far, the MTA has completed a new bike/pedestrian ramp connecting the northern walkway of the Manhattan span of the Robert F. Kennedy Bridge that will connect to the future East River Greenway in East Harlem.

Ad Loading...

The MTA is replacing and widening the Henry Hudson Bridge’s lower-level walkway to build ADA-compliant ramps on both sides of the bridge and provide better connectivity between Spuyten Duyvil in the Bronx and Inwood Hill Park in Manhattan. This is expected to be completed by the end of 2024. Similar work is happening on the Cross Bay Bridge between Broad Channel and Rockaway Beach.

During its December meeting, the MTA Board approved the award of a contract that will create a new bike/pedestrian shared-use path to replace the current walkway across the RFK’s East River suspension and Queens approach structure, providing an ADA accessible connection between Astoria and Wards/Randall’s Island. The MTA will complete this work by the end of 2027. 

The MTA is also constructing end-to-end ADA connectivity between Randall’s Island, Manhattan, and the Bronx. This work is expected to be completed by the end of 2024.

More Management

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
New Mobilityby StaffJanuary 30, 2026

Chicago's Pace Expands VanGo Mobility Program

The service is a flexible, reservation-based transit service designed to close the first- and last-mile gaps and connect riders to employment for just $5 per day.

Read More →
A blue and white graphic with text reading "Foothill Gold Line: Design Contract Award & 2026 Board Leadership."
Managementby StaffJanuary 30, 2026

Foothill Gold Line Board Awards Claremont Extension Design Contract to Parsons, Maintains Board Leadership for 2026

Parsons wins the $60M Claremont Extension design contract as the Foothill Gold Line board reaffirms leadership during a pivotal project phase.

Read More →
Ad Loading...
Technologyby StaffJanuary 29, 2026

Houston METRO Introduces RideMETRO Fare System

The upgraded system, which went live earlier this month, supports METRO’s METRONow vision to enhance the customer experience, improve service reliability, and strengthen long-term regional mobility.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
A b2x rewards logo and graphic reading "Read. Learn. Earn."
Managementby StaffJanuary 29, 2026

Bobit Business Media Launches B2X Rewards to Engage Transit Industry Professionals

The new program rewards B2B audience readers for engaging with trusted content and suppliers, earning them points toward events, travel, and more.

Read More →
Ad Loading...
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Busby StaffJanuary 28, 2026

New Orleans RTA Reaches Agreement with ATU

The agreement provides competitive wages and reflects strong labor-management collaboration, positive working relationships, and a shared commitment to building a world-class transit system for the community, said RTA CEO Lona Edwards Hankins.

Read More →
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Ad Loading...
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →