Santa Clara VTA Confirms Single Bore Design for BART Silicon Valley Phase II

The agency has endorsed a large single-bore tunnel as the preferred design for Phase II, citing reduced risk, lower costs, and minimal downtown disruption.

Construction workers guide material hanging from a crane.

Construction of the tunnel boring machine entrance is underway at the BART Silicon Valley Phase II West Portal site in Santa Clara.

Photo: Valley Transportation Authority

2 min to read


The Santa Clara Valley Transportation Authority (VTA) has confirmed the large single bore as the preferred tunnel configuration for BART Silicon Valley Phase II, following a peer review conducted by tunneling and transit experts from major transit agencies across the country.

The VTA Board of Directors, in a special meeting recently, heard an extensive presentation on the peer review and its recommendations on moving forward with the largest public infrastructure project in Santa Clara County.

Ad Loading...

Following the discussion, the board voted in favor of the single bore as the most viable option, offering the best balance of constructability, feasibility, and lower overall risk. According to an agency release, it avoids the high cost, complexity, and downtown disruption associated with an alternative concurrent tunneling approach of using two boring machines.

This alternative would have required a cut-and-cover excavation in the heart of San Jose. The board’s decision allows VTA to advance project design towards 60% and meet the projected revenue service date.

The panel also included recommendations to ensure greater cost estimation, accuracy and budget alignment, reduce schedule delays and manage tunnel risk.

VTA Reinforces Tunneling Team and Industry Partnerships

With VTA now owning the Tunnel Boring Machine (TBM), the agency assumes full responsibility for its performance. To manage this risk, VTA will deploy a top-tier tunneling team and embed Herrenknecht engineers to support operations and reduce delays.

The panel also highlighted the limited pool of qualified contractors and skilled labor for large diameter tunneling. VTA will continue early engagement with the industry to secure experienced construction teams and develop a contract strategy toincreasebidder participation.

Ad Loading...

Lastly, according to the release, the peer review reinforces the importance of a strong VTA-BART partnership. Both agencies have agreed to reestablishing regular touchpoints and prioritizing communications between agencies.

More Management

A tan, blue, and green graphic with text reading "Record Ridership: World Cup 2026."
Managementby Elora HaynesJune 18, 2026

FIFA World Cup Matches Are Driving Record Transit Ridership Nationwide

See how World Cup matches are generating record transit demand across North America, with ridership surpassing Super Bowls, concerts, and Olympic-era events.

Read More →
Zero-emissions bus with FLEETWATCH technology
ManagementJune 17, 2026

The Hidden Cost of Fuel Data Inaccuracy in Public Transit Fleets

In today's transit environment, accurate fuel and mileage data are critical to reducing costs, minimizing downtime, and improving fleet performance.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Ad Loading...
A color graphic with LIT's logo and text reading "Now Accepting 2027 Host City Proposals."
Managementby Staff and News ReportsJune 17, 2026

Latinos In Transit Seeks Host Organization for 2027 Leadership Summit

The selected host organization will showcase its transit system, projects, and community while welcoming hundreds of industry leaders and emerging professionals during Hispanic Heritage Month.

Read More →
Group announcing BUSES Act
Motorcoachby StaffJune 16, 2026

Bipartisan BUSES Act Seeks Changes to New York City's Bus Idling Enforcement Program

Backed by motorcoach operators, the legislation seeks to balance emissions goals with passenger safety by allowing limited idling for inspections, accessibility needs and extreme weather conditions.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
Manhattan Congestion Relief Zone Sees Traffic Reduction
Managementby StaffJune 15, 2026

Q4 Travel Data Reveals Drop in Vehicle Traffic to Manhattan Congestion Zone

NYMTC’s quarterly Travel Patterns Report provides a snapshot of travel activity throughout New York City, Long Island, the Lower Hudson Valley, and northern New Jersey using data collected from the agencies operating the region’s bridges, tunnels, and public transit systems.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
Ad Loading...
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →